HOT-ROLLED FLAT-ROLLED CARBON-QUALITY STEEL PRODUCTS
AD INVESTIGATION TIMETABLE Based on Prelim at 120 Days PUBLIC VERSION |
|---|
| Day from Initiation |
Action |
Calendar Due Date |
|---|---|---|
| Petition filed | 09/30/98 | |
| Deficiency questionnaire to petitioner | 10/06/98 | |
| Deficiency questionnaire returned | 10/09/98 | |
| 0 | ITA Initiation | 10/15/98 |
| 1 | ITA cables US embassy for foreign producer list | 10/16/98 |
| 4 | Model Match Request for Comments | 10/19/98 |
| 5 | Section A Questionnaire Sent Out | 10/20/98 |
| 7 | Model Match Comments Due | 10/22/98 |
| 11 | If appropriate, 4 Day Extension on Model Match Comments | 10/26/98 |
| 12 | ITA questionnaire sent to respondent | 10/30/98 |
| 25 | Section A Response due | 11/09/98 |
| 29 | ITC preliminary injury determination* | 11/13/98 |
| 32 | If appropriate, 7 Day Extension of Section A Response | 11/16/98 |
| 52 | Questionnaire Response for B, C, and D due | 12/06/98 |
| 67 | If appropriate, 15 Day Extension on Questionnaire Response | 12/21/98 |
| 74 | Petitioners Comments on Response Due | 12/28/98 |
| 81 | ITA sends deficiency questionnaire | 01/04/99 |
| 95 | Deficiency Questionnaire Response Due | 01/18/99 |
| 102 | If appropriate, 7 Day Extension on Deficiency Response | 01/25/99 |
| 120 | Preliminary Determination | 02/12/99 |
| 202 | Final Determination** | 05/05/99 |
| * | Note: ITC Preliminary Determination Date is within 45 days of ITA's initiation.
In this case, 45 days from initiation is Sunday, November 15. |
| ** | Final Determination = Preliminary Determination Date + 7 Days for publication in FR (estimated) + 75 Days (statutory) |